Court Sides With Louisville: One Touch Make Ready Is A-Ok

Louisville has overcome a tall hurdle in its efforts to bring better connectivity and more competition to the community through local control. On August 16th the U.S. District Court for the Western District of Kentucky supported the city’s one touch make ready (OTMR) ordinance. AT&T challenged the ordinance in court, but their arguments fell flat and court confirmed that the city has the authority to manage its rights-of-way with OTMR.

State Law

AT&T’s claim based on state law asserted that the city was overstepping its authority by enacting the OTMR ordinance because it was impinging on Kentucky Public Service Commission jurisdiction. AT&T attorneys argued that, according to state law, the PSC has exclusive jurisdiction over utility rates and services, but the court found that argument incorrect.

Within the state law, the court found that the OTMR ordinance fell under a carve-out that allows Louisville to retain jurisdiction over its public rights-of-way as a matter of public safety. The ordinance helps limit traffic disruptions by reducing the number of instances trucks and crews need to tend to pole attachments. The court wrote in its Order:

AT&T narrowly characterizes Ordinance No. 21 as one that regulates pole attachments. But the ordinance actually prescribes the “method or manner of encumbering or placing burdens on” public rights-of-way. … It is undisputed that make-ready work can require blocking traffic and sidewalks multiple times to permit multiple crews to perform the same work on the same utility pole…. The one-touch make-ready ordinance requires that all necessary make-ready work be performed by a single crew, lessening the impact of make-ready work on public rights-of-way. … Louisville Metro has an important interest in managing its public rights-of-way to maximize efficiency and enhance public safety. … And Kentucky law preserves the right of cities to regulate public rights-of-way. … Because Ordinance No. 21 regulates public rights-of-way, it is within Louisville Metro’s constitutional authority to enact the ordinance, and [the state law granting authority to the PSC] cannot limit that authority. 

Federal Jurisdiction

Court Sides With Louisville: One Touch Make Ready Is A-Ok

Louisville has overcome a tall hurdle in its efforts to bring better connectivity and more competition to the community through local control. On August 16th the U.S. District Court for the Western District of Kentucky supported the city’s one touch make ready (OTMR) ordinance. AT&T challenged the ordinance in court, but their arguments fell flat and court confirmed that the city has the authority to manage its rights-of-way with OTMR.

State Law

AT&T’s claim based on state law asserted that the city was overstepping its authority by enacting the OTMR ordinance because it was impinging on Kentucky Public Service Commission jurisdiction. AT&T attorneys argued that, according to state law, the PSC has exclusive jurisdiction over utility rates and services, but the court found that argument incorrect.

Within the state law, the court found that the OTMR ordinance fell under a carve-out that allows Louisville to retain jurisdiction over its public rights-of-way as a matter of public safety. The ordinance helps limit traffic disruptions by reducing the number of instances trucks and crews need to tend to pole attachments. The court wrote in its Order:

AT&T narrowly characterizes Ordinance No. 21 as one that regulates pole attachments. But the ordinance actually prescribes the “method or manner of encumbering or placing burdens on” public rights-of-way. … It is undisputed that make-ready work can require blocking traffic and sidewalks multiple times to permit multiple crews to perform the same work on the same utility pole…. The one-touch make-ready ordinance requires that all necessary make-ready work be performed by a single crew, lessening the impact of make-ready work on public rights-of-way. … Louisville Metro has an important interest in managing its public rights-of-way to maximize efficiency and enhance public safety. … And Kentucky law preserves the right of cities to regulate public rights-of-way. … Because Ordinance No. 21 regulates public rights-of-way, it is within Louisville Metro’s constitutional authority to enact the ordinance, and [the state law granting authority to the PSC] cannot limit that authority. 

Federal Jurisdiction

One Touch Make Ready: Model Language In Three Cities And Counting...

One Touch Make Ready (OTMR) policies are recognized as a way to cut down on the expense and the time it takes to deploy fiber optic networks. At least three sizable urban communities have adopted OTMR practices to streamline fiber optic construction and ensure consistent standards. For other communities looking at ways to encourage brisk fiber optic investment, it pays to study the language of OTMR resolutions and policies.

OTMR allows a pre-approved contractor to move cables belonging to more than one entity on one visit to the pole to make room for the new fiber optic cable. This is a departure from the old method, in which each entity takes turns visiting the pole in question to move only their wires. The old approach is time consuming because each entity must take turns in the order in which their wires are installed on the poles. If one entity causes a delay, every other entity that needs to work after them must also wait. What follows is a snowball effect and an entire project can fall far behind schedule.

San Antonio, Texas

San Antonio’s municipal utility, CPS Energy, adopted a broad set of pole attachment standards that include specific requirements for OTMR, including what needs to happen before, during, and after the process.

The standards lay out administrative procedures, technical provisions, and specific provisions for both wired and wireless attachments. It incorporates recommendations from the FCC on how best to expand broadband while also weaving in safety standards from the Occupational Safety and Health Administration (OSHA). In the introduction, CPS Energy writes:

From a holistic perspective, the Standards seek to balance the competing needs and interests of multiple communications providers to access and utilize CPS Energy Poles, while at the same time recognizing that the core purpose and function of these Poles is for CPS Energy’s safe and reliable distribution and delivery of electric services to CPS Energy customers. Hence, any use of CPS Energy’s Poles must at all times ensure the continued operational integrity, safety and reliability of CPS Energy’s Facilities, electric services, personnel and the general public.

One Touch Make Ready: Model Language In Three Cities And Counting...

One Touch Make Ready (OTMR) policies are recognized as a way to cut down on the expense and the time it takes to deploy fiber optic networks. At least three sizable urban communities have adopted OTMR practices to streamline fiber optic construction and ensure consistent standards. For other communities looking at ways to encourage brisk fiber optic investment, it pays to study the language of OTMR resolutions and policies.

OTMR allows a pre-approved contractor to move cables belonging to more than one entity on one visit to the pole to make room for the new fiber optic cable. This is a departure from the old method, in which each entity takes turns visiting the pole in question to move only their wires. The old approach is time consuming because each entity must take turns in the order in which their wires are installed on the poles. If one entity causes a delay, every other entity that needs to work after them must also wait. What follows is a snowball effect and an entire project can fall far behind schedule.

San Antonio, Texas

San Antonio’s municipal utility, CPS Energy, adopted a broad set of pole attachment standards that include specific requirements for OTMR, including what needs to happen before, during, and after the process.

The standards lay out administrative procedures, technical provisions, and specific provisions for both wired and wireless attachments. It incorporates recommendations from the FCC on how best to expand broadband while also weaving in safety standards from the Occupational Safety and Health Administration (OSHA). In the introduction, CPS Energy writes:

From a holistic perspective, the Standards seek to balance the competing needs and interests of multiple communications providers to access and utilize CPS Energy Poles, while at the same time recognizing that the core purpose and function of these Poles is for CPS Energy’s safe and reliable distribution and delivery of electric services to CPS Energy customers. Hence, any use of CPS Energy’s Poles must at all times ensure the continued operational integrity, safety and reliability of CPS Energy’s Facilities, electric services, personnel and the general public.

One Touch Make Ready: Model Language In Three Cities And Counting...

One Touch Make Ready (OTMR) policies are recognized as a way to cut down on the expense and the time it takes to deploy fiber optic networks. At least three sizable urban communities have adopted OTMR practices to streamline fiber optic construction and ensure consistent standards. For other communities looking at ways to encourage brisk fiber optic investment, it pays to study the language of OTMR resolutions and policies.

OTMR allows a pre-approved contractor to move cables belonging to more than one entity on one visit to the pole to make room for the new fiber optic cable. This is a departure from the old method, in which each entity takes turns visiting the pole in question to move only their wires. The old approach is time consuming because each entity must take turns in the order in which their wires are installed on the poles. If one entity causes a delay, every other entity that needs to work after them must also wait. What follows is a snowball effect and an entire project can fall far behind schedule.

San Antonio, Texas

San Antonio’s municipal utility, CPS Energy, adopted a broad set of pole attachment standards that include specific requirements for OTMR, including what needs to happen before, during, and after the process.

The standards lay out administrative procedures, technical provisions, and specific provisions for both wired and wireless attachments. It incorporates recommendations from the FCC on how best to expand broadband while also weaving in safety standards from the Occupational Safety and Health Administration (OSHA). In the introduction, CPS Energy writes:

From a holistic perspective, the Standards seek to balance the competing needs and interests of multiple communications providers to access and utilize CPS Energy Poles, while at the same time recognizing that the core purpose and function of these Poles is for CPS Energy’s safe and reliable distribution and delivery of electric services to CPS Energy customers. Hence, any use of CPS Energy’s Poles must at all times ensure the continued operational integrity, safety and reliability of CPS Energy’s Facilities, electric services, personnel and the general public.

One Touch Make Ready: Model Language In Three Cities And Counting...

One Touch Make Ready (OTMR) policies are recognized as a way to cut down on the expense and the time it takes to deploy fiber optic networks. At least three sizable urban communities have adopted OTMR practices to streamline fiber optic construction and ensure consistent standards. For other communities looking at ways to encourage brisk fiber optic investment, it pays to study the language of OTMR resolutions and policies.

OTMR allows a pre-approved contractor to move cables belonging to more than one entity on one visit to the pole to make room for the new fiber optic cable. This is a departure from the old method, in which each entity takes turns visiting the pole in question to move only their wires. The old approach is time consuming because each entity must take turns in the order in which their wires are installed on the poles. If one entity causes a delay, every other entity that needs to work after them must also wait. What follows is a snowball effect and an entire project can fall far behind schedule.

San Antonio, Texas

San Antonio’s municipal utility, CPS Energy, adopted a broad set of pole attachment standards that include specific requirements for OTMR, including what needs to happen before, during, and after the process.

The standards lay out administrative procedures, technical provisions, and specific provisions for both wired and wireless attachments. It incorporates recommendations from the FCC on how best to expand broadband while also weaving in safety standards from the Occupational Safety and Health Administration (OSHA). In the introduction, CPS Energy writes:

From a holistic perspective, the Standards seek to balance the competing needs and interests of multiple communications providers to access and utilize CPS Energy Poles, while at the same time recognizing that the core purpose and function of these Poles is for CPS Energy’s safe and reliable distribution and delivery of electric services to CPS Energy customers. Hence, any use of CPS Energy’s Poles must at all times ensure the continued operational integrity, safety and reliability of CPS Energy’s Facilities, electric services, personnel and the general public.

One Touch Make Ready: Model Language In Three Cities And Counting...

One Touch Make Ready (OTMR) policies are recognized as a way to cut down on the expense and the time it takes to deploy fiber optic networks. At least three sizable urban communities have adopted OTMR practices to streamline fiber optic construction and ensure consistent standards. For other communities looking at ways to encourage brisk fiber optic investment, it pays to study the language of OTMR resolutions and policies.

OTMR allows a pre-approved contractor to move cables belonging to more than one entity on one visit to the pole to make room for the new fiber optic cable. This is a departure from the old method, in which each entity takes turns visiting the pole in question to move only their wires. The old approach is time consuming because each entity must take turns in the order in which their wires are installed on the poles. If one entity causes a delay, every other entity that needs to work after them must also wait. What follows is a snowball effect and an entire project can fall far behind schedule.

San Antonio, Texas

San Antonio’s municipal utility, CPS Energy, adopted a broad set of pole attachment standards that include specific requirements for OTMR, including what needs to happen before, during, and after the process.

The standards lay out administrative procedures, technical provisions, and specific provisions for both wired and wireless attachments. It incorporates recommendations from the FCC on how best to expand broadband while also weaving in safety standards from the Occupational Safety and Health Administration (OSHA). In the introduction, CPS Energy writes:

From a holistic perspective, the Standards seek to balance the competing needs and interests of multiple communications providers to access and utilize CPS Energy Poles, while at the same time recognizing that the core purpose and function of these Poles is for CPS Energy’s safe and reliable distribution and delivery of electric services to CPS Energy customers. Hence, any use of CPS Energy’s Poles must at all times ensure the continued operational integrity, safety and reliability of CPS Energy’s Facilities, electric services, personnel and the general public.

One Touch Make Ready: Model Language In Three Cities And Counting...

One Touch Make Ready (OTMR) policies are recognized as a way to cut down on the expense and the time it takes to deploy fiber optic networks. At least three sizable urban communities have adopted OTMR practices to streamline fiber optic construction and ensure consistent standards. For other communities looking at ways to encourage brisk fiber optic investment, it pays to study the language of OTMR resolutions and policies.

OTMR allows a pre-approved contractor to move cables belonging to more than one entity on one visit to the pole to make room for the new fiber optic cable. This is a departure from the old method, in which each entity takes turns visiting the pole in question to move only their wires. The old approach is time consuming because each entity must take turns in the order in which their wires are installed on the poles. If one entity causes a delay, every other entity that needs to work after them must also wait. What follows is a snowball effect and an entire project can fall far behind schedule.

San Antonio, Texas

San Antonio’s municipal utility, CPS Energy, adopted a broad set of pole attachment standards that include specific requirements for OTMR, including what needs to happen before, during, and after the process.

The standards lay out administrative procedures, technical provisions, and specific provisions for both wired and wireless attachments. It incorporates recommendations from the FCC on how best to expand broadband while also weaving in safety standards from the Occupational Safety and Health Administration (OSHA). In the introduction, CPS Energy writes:

From a holistic perspective, the Standards seek to balance the competing needs and interests of multiple communications providers to access and utilize CPS Energy Poles, while at the same time recognizing that the core purpose and function of these Poles is for CPS Energy’s safe and reliable distribution and delivery of electric services to CPS Energy customers. Hence, any use of CPS Energy’s Poles must at all times ensure the continued operational integrity, safety and reliability of CPS Energy’s Facilities, electric services, personnel and the general public.

One Touch Make Ready: Model Language In Three Cities And Counting...

One Touch Make Ready (OTMR) policies are recognized as a way to cut down on the expense and the time it takes to deploy fiber optic networks. At least three sizable urban communities have adopted OTMR practices to streamline fiber optic construction and ensure consistent standards. For other communities looking at ways to encourage brisk fiber optic investment, it pays to study the language of OTMR resolutions and policies.

OTMR allows a pre-approved contractor to move cables belonging to more than one entity on one visit to the pole to make room for the new fiber optic cable. This is a departure from the old method, in which each entity takes turns visiting the pole in question to move only their wires. The old approach is time consuming because each entity must take turns in the order in which their wires are installed on the poles. If one entity causes a delay, every other entity that needs to work after them must also wait. What follows is a snowball effect and an entire project can fall far behind schedule.

San Antonio, Texas

San Antonio’s municipal utility, CPS Energy, adopted a broad set of pole attachment standards that include specific requirements for OTMR, including what needs to happen before, during, and after the process.

The standards lay out administrative procedures, technical provisions, and specific provisions for both wired and wireless attachments. It incorporates recommendations from the FCC on how best to expand broadband while also weaving in safety standards from the Occupational Safety and Health Administration (OSHA). In the introduction, CPS Energy writes:

From a holistic perspective, the Standards seek to balance the competing needs and interests of multiple communications providers to access and utilize CPS Energy Poles, while at the same time recognizing that the core purpose and function of these Poles is for CPS Energy’s safe and reliable distribution and delivery of electric services to CPS Energy customers. Hence, any use of CPS Energy’s Poles must at all times ensure the continued operational integrity, safety and reliability of CPS Energy’s Facilities, electric services, personnel and the general public.

One Touch Make Ready: Model Language In Three Cities And Counting...

One Touch Make Ready (OTMR) policies are recognized as a way to cut down on the expense and the time it takes to deploy fiber optic networks. At least three sizable urban communities have adopted OTMR practices to streamline fiber optic construction and ensure consistent standards. For other communities looking at ways to encourage brisk fiber optic investment, it pays to study the language of OTMR resolutions and policies.

OTMR allows a pre-approved contractor to move cables belonging to more than one entity on one visit to the pole to make room for the new fiber optic cable. This is a departure from the old method, in which each entity takes turns visiting the pole in question to move only their wires. The old approach is time consuming because each entity must take turns in the order in which their wires are installed on the poles. If one entity causes a delay, every other entity that needs to work after them must also wait. What follows is a snowball effect and an entire project can fall far behind schedule.

San Antonio, Texas

San Antonio’s municipal utility, CPS Energy, adopted a broad set of pole attachment standards that include specific requirements for OTMR, including what needs to happen before, during, and after the process.

The standards lay out administrative procedures, technical provisions, and specific provisions for both wired and wireless attachments. It incorporates recommendations from the FCC on how best to expand broadband while also weaving in safety standards from the Occupational Safety and Health Administration (OSHA). In the introduction, CPS Energy writes:

From a holistic perspective, the Standards seek to balance the competing needs and interests of multiple communications providers to access and utilize CPS Energy Poles, while at the same time recognizing that the core purpose and function of these Poles is for CPS Energy’s safe and reliable distribution and delivery of electric services to CPS Energy customers. Hence, any use of CPS Energy’s Poles must at all times ensure the continued operational integrity, safety and reliability of CPS Energy’s Facilities, electric services, personnel and the general public.