Explaining Right-of-Way Basics - Community Broadband Bits Episode 169

For this week's Community Broadband Bits, we are delving into an area of law and practice that is quite important for Internet network deployment but tends to be dry and confusing. Not for us today though, we have Sean Stokes, a Principal at Baller Herbst Stokes & Lide, joining us to explain Right-of-Way basics. We talk about what the public Right-of-Way (ROW) is, who is responsible for maintaining it, how entities can get access to it and how poles are distinct from the ROW. We discuss how much power local governments and pole owners have to deny access to these assets and some of the costs associated with make-ready. 

If you don't know what make-ready is, you'll know in less than thirty minutes. We finish our discussion by exploring the "Municipal Gain" policy in Connecticut, where munis are entitled to some space on the poles for any purpose they choose to use it. Historically, this was used only for public safety, but it was recently broadened. Sean also explores how he believes we should simplify access for fiber-optics rather than basing access on the particular end service being offered. 

This show is 30 minutes long and can be played on this page or via Apple Podcasts or the tool of your choice using this feed.

Transcript below.

We want your feedback and suggestions for the show-please e-mail us or leave a comment below.

Listen to other episodes here or view all episodes in our index. See other podcasts from the Institute for Local Self-Reliance here.

Thanks to bkfm-b-side for the music, licensed using Creative Commons. The song is "Raise Your Hands."

Explaining Right-of-Way Basics - Community Broadband Bits Episode 169

For this week's Community Broadband Bits, we are delving into an area of law and practice that is quite important for Internet network deployment but tends to be dry and confusing. Not for us today though, we have Sean Stokes, a Principal at Baller Herbst Stokes & Lide, joining us to explain Right-of-Way basics. We talk about what the public Right-of-Way (ROW) is, who is responsible for maintaining it, how entities can get access to it and how poles are distinct from the ROW. We discuss how much power local governments and pole owners have to deny access to these assets and some of the costs associated with make-ready. 

If you don't know what make-ready is, you'll know in less than thirty minutes. We finish our discussion by exploring the "Municipal Gain" policy in Connecticut, where munis are entitled to some space on the poles for any purpose they choose to use it. Historically, this was used only for public safety, but it was recently broadened. Sean also explores how he believes we should simplify access for fiber-optics rather than basing access on the particular end service being offered. 

This show is 30 minutes long and can be played on this page or via Apple Podcasts or the tool of your choice using this feed.

Transcript below.

We want your feedback and suggestions for the show-please e-mail us or leave a comment below.

Listen to other episodes here or view all episodes in our index. See other podcasts from the Institute for Local Self-Reliance here.

Thanks to bkfm-b-side for the music, licensed using Creative Commons. The song is "Raise Your Hands."

Explaining Right-of-Way Basics - Community Broadband Bits Episode 169

For this week's Community Broadband Bits, we are delving into an area of law and practice that is quite important for Internet network deployment but tends to be dry and confusing. Not for us today though, we have Sean Stokes, a Principal at Baller Herbst Stokes & Lide, joining us to explain Right-of-Way basics. We talk about what the public Right-of-Way (ROW) is, who is responsible for maintaining it, how entities can get access to it and how poles are distinct from the ROW. We discuss how much power local governments and pole owners have to deny access to these assets and some of the costs associated with make-ready. 

If you don't know what make-ready is, you'll know in less than thirty minutes. We finish our discussion by exploring the "Municipal Gain" policy in Connecticut, where munis are entitled to some space on the poles for any purpose they choose to use it. Historically, this was used only for public safety, but it was recently broadened. Sean also explores how he believes we should simplify access for fiber-optics rather than basing access on the particular end service being offered. 

This show is 30 minutes long and can be played on this page or via Apple Podcasts or the tool of your choice using this feed.

Transcript below.

We want your feedback and suggestions for the show-please e-mail us or leave a comment below.

Listen to other episodes here or view all episodes in our index. See other podcasts from the Institute for Local Self-Reliance here.

Thanks to bkfm-b-side for the music, licensed using Creative Commons. The song is "Raise Your Hands."

Explaining Right-of-Way Basics - Community Broadband Bits Episode 169

For this week's Community Broadband Bits, we are delving into an area of law and practice that is quite important for Internet network deployment but tends to be dry and confusing. Not for us today though, we have Sean Stokes, a Principal at Baller Herbst Stokes & Lide, joining us to explain Right-of-Way basics. We talk about what the public Right-of-Way (ROW) is, who is responsible for maintaining it, how entities can get access to it and how poles are distinct from the ROW. We discuss how much power local governments and pole owners have to deny access to these assets and some of the costs associated with make-ready. 

If you don't know what make-ready is, you'll know in less than thirty minutes. We finish our discussion by exploring the "Municipal Gain" policy in Connecticut, where munis are entitled to some space on the poles for any purpose they choose to use it. Historically, this was used only for public safety, but it was recently broadened. Sean also explores how he believes we should simplify access for fiber-optics rather than basing access on the particular end service being offered. 

This show is 30 minutes long and can be played on this page or via Apple Podcasts or the tool of your choice using this feed.

Transcript below.

We want your feedback and suggestions for the show-please e-mail us or leave a comment below.

Listen to other episodes here or view all episodes in our index. See other podcasts from the Institute for Local Self-Reliance here.

Thanks to bkfm-b-side for the music, licensed using Creative Commons. The song is "Raise Your Hands."

Princeton Voters Authorize FTTH Make-Ready Funds in Record Turn-Out

On November 18th, 90% of voters at Princeton's special town meeting approved a measure to fund $1.2 million in make-ready costs bringing the community one step closer to fiber connectivity. The number voters who attended the meeting broke the previous attendance record set 15 years ago by 30%.

We introduced the central Massachusetts town of 3,300 in 2013. The community suffered from poor Internet connectivity negatively impacting its schools, real estate market, and economic development. Since then, the community voted to create a Municipal Light Plant and to appropriate funds to keep the project moving forward.

Community leaders have investigated several options and last fall entered into a relationship with the Matrix Design Group. According to the Memorandum of Understanding [PDF], Matrix will design, build, and operate the FTTH network for a period of 20 years. At the end of that time period, Princeton Broadband Municipal Light Plant has the option of renewing that relationship or purchasing the network for $1.

As their contribution, Princeton will provide rights-of-way, police details during construction, powered telecom shelters, and will pay for utility pole make-ready costs. According to an article in the Landmark:

The make ready work includes replacing approximately 80 utility poles, and moving telephone and electrical lines on 450 poles, providing housing for the electrical components needed to operate the system, and paying for police details during the make ready work.

The borrowing is expected to cost the owner of a home valued at $300,000, about $10 a month or $115 a year increase on their taxes for 12 years. Internet service plus telephone will cost $115 a month. Once a contract is negotiated with Matrix, construction on the make ready phase would start in January 2015 and the project would be completed by January 2016.

Princeton Voters Authorize FTTH Make-Ready Funds in Record Turn-Out

On November 18th, 90% of voters at Princeton's special town meeting approved a measure to fund $1.2 million in make-ready costs bringing the community one step closer to fiber connectivity. The number voters who attended the meeting broke the previous attendance record set 15 years ago by 30%.

We introduced the central Massachusetts town of 3,300 in 2013. The community suffered from poor Internet connectivity negatively impacting its schools, real estate market, and economic development. Since then, the community voted to create a Municipal Light Plant and to appropriate funds to keep the project moving forward.

Community leaders have investigated several options and last fall entered into a relationship with the Matrix Design Group. According to the Memorandum of Understanding [PDF], Matrix will design, build, and operate the FTTH network for a period of 20 years. At the end of that time period, Princeton Broadband Municipal Light Plant has the option of renewing that relationship or purchasing the network for $1.

As their contribution, Princeton will provide rights-of-way, police details during construction, powered telecom shelters, and will pay for utility pole make-ready costs. According to an article in the Landmark:

The make ready work includes replacing approximately 80 utility poles, and moving telephone and electrical lines on 450 poles, providing housing for the electrical components needed to operate the system, and paying for police details during the make ready work.

The borrowing is expected to cost the owner of a home valued at $300,000, about $10 a month or $115 a year increase on their taxes for 12 years. Internet service plus telephone will cost $115 a month. Once a contract is negotiated with Matrix, construction on the make ready phase would start in January 2015 and the project would be completed by January 2016.

Princeton Voters Authorize FTTH Make-Ready Funds in Record Turn-Out

On November 18th, 90% of voters at Princeton's special town meeting approved a measure to fund $1.2 million in make-ready costs bringing the community one step closer to fiber connectivity. The number voters who attended the meeting broke the previous attendance record set 15 years ago by 30%.

We introduced the central Massachusetts town of 3,300 in 2013. The community suffered from poor Internet connectivity negatively impacting its schools, real estate market, and economic development. Since then, the community voted to create a Municipal Light Plant and to appropriate funds to keep the project moving forward.

Community leaders have investigated several options and last fall entered into a relationship with the Matrix Design Group. According to the Memorandum of Understanding [PDF], Matrix will design, build, and operate the FTTH network for a period of 20 years. At the end of that time period, Princeton Broadband Municipal Light Plant has the option of renewing that relationship or purchasing the network for $1.

As their contribution, Princeton will provide rights-of-way, police details during construction, powered telecom shelters, and will pay for utility pole make-ready costs. According to an article in the Landmark:

The make ready work includes replacing approximately 80 utility poles, and moving telephone and electrical lines on 450 poles, providing housing for the electrical components needed to operate the system, and paying for police details during the make ready work.

The borrowing is expected to cost the owner of a home valued at $300,000, about $10 a month or $115 a year increase on their taxes for 12 years. Internet service plus telephone will cost $115 a month. Once a contract is negotiated with Matrix, construction on the make ready phase would start in January 2015 and the project would be completed by January 2016.

Princeton Voters Authorize FTTH Make-Ready Funds in Record Turn-Out

On November 18th, 90% of voters at Princeton's special town meeting approved a measure to fund $1.2 million in make-ready costs bringing the community one step closer to fiber connectivity. The number voters who attended the meeting broke the previous attendance record set 15 years ago by 30%.

We introduced the central Massachusetts town of 3,300 in 2013. The community suffered from poor Internet connectivity negatively impacting its schools, real estate market, and economic development. Since then, the community voted to create a Municipal Light Plant and to appropriate funds to keep the project moving forward.

Community leaders have investigated several options and last fall entered into a relationship with the Matrix Design Group. According to the Memorandum of Understanding [PDF], Matrix will design, build, and operate the FTTH network for a period of 20 years. At the end of that time period, Princeton Broadband Municipal Light Plant has the option of renewing that relationship or purchasing the network for $1.

As their contribution, Princeton will provide rights-of-way, police details during construction, powered telecom shelters, and will pay for utility pole make-ready costs. According to an article in the Landmark:

The make ready work includes replacing approximately 80 utility poles, and moving telephone and electrical lines on 450 poles, providing housing for the electrical components needed to operate the system, and paying for police details during the make ready work.

The borrowing is expected to cost the owner of a home valued at $300,000, about $10 a month or $115 a year increase on their taxes for 12 years. Internet service plus telephone will cost $115 a month. Once a contract is negotiated with Matrix, construction on the make ready phase would start in January 2015 and the project would be completed by January 2016.

Princeton Voters Authorize FTTH Make-Ready Funds in Record Turn-Out

On November 18th, 90% of voters at Princeton's special town meeting approved a measure to fund $1.2 million in make-ready costs bringing the community one step closer to fiber connectivity. The number voters who attended the meeting broke the previous attendance record set 15 years ago by 30%.

We introduced the central Massachusetts town of 3,300 in 2013. The community suffered from poor Internet connectivity negatively impacting its schools, real estate market, and economic development. Since then, the community voted to create a Municipal Light Plant and to appropriate funds to keep the project moving forward.

Community leaders have investigated several options and last fall entered into a relationship with the Matrix Design Group. According to the Memorandum of Understanding [PDF], Matrix will design, build, and operate the FTTH network for a period of 20 years. At the end of that time period, Princeton Broadband Municipal Light Plant has the option of renewing that relationship or purchasing the network for $1.

As their contribution, Princeton will provide rights-of-way, police details during construction, powered telecom shelters, and will pay for utility pole make-ready costs. According to an article in the Landmark:

The make ready work includes replacing approximately 80 utility poles, and moving telephone and electrical lines on 450 poles, providing housing for the electrical components needed to operate the system, and paying for police details during the make ready work.

The borrowing is expected to cost the owner of a home valued at $300,000, about $10 a month or $115 a year increase on their taxes for 12 years. Internet service plus telephone will cost $115 a month. Once a contract is negotiated with Matrix, construction on the make ready phase would start in January 2015 and the project would be completed by January 2016.

Princeton Voters Authorize FTTH Make-Ready Funds in Record Turn-Out

On November 18th, 90% of voters at Princeton's special town meeting approved a measure to fund $1.2 million in make-ready costs bringing the community one step closer to fiber connectivity. The number voters who attended the meeting broke the previous attendance record set 15 years ago by 30%.

We introduced the central Massachusetts town of 3,300 in 2013. The community suffered from poor Internet connectivity negatively impacting its schools, real estate market, and economic development. Since then, the community voted to create a Municipal Light Plant and to appropriate funds to keep the project moving forward.

Community leaders have investigated several options and last fall entered into a relationship with the Matrix Design Group. According to the Memorandum of Understanding [PDF], Matrix will design, build, and operate the FTTH network for a period of 20 years. At the end of that time period, Princeton Broadband Municipal Light Plant has the option of renewing that relationship or purchasing the network for $1.

As their contribution, Princeton will provide rights-of-way, police details during construction, powered telecom shelters, and will pay for utility pole make-ready costs. According to an article in the Landmark:

The make ready work includes replacing approximately 80 utility poles, and moving telephone and electrical lines on 450 poles, providing housing for the electrical components needed to operate the system, and paying for police details during the make ready work.

The borrowing is expected to cost the owner of a home valued at $300,000, about $10 a month or $115 a year increase on their taxes for 12 years. Internet service plus telephone will cost $115 a month. Once a contract is negotiated with Matrix, construction on the make ready phase would start in January 2015 and the project would be completed by January 2016.